A reserve study lists everything the association will one day have to repair or replace, such as the roof, the boiler, the elevator and the paving, with what each will cost and when. It then works out how much to set aside each year so the money is there when the work comes due. Without one, a board finds out what the roof costs the year it fails, and owners get a special assessment.
Most states leave it to the board. Eleven don’t. Florida’s law came after the Champlain Towers South collapse in Surfside in 2021, and New York is among the states considering one.
The eleven states
| State | How often | Whom it covers |
|---|---|---|
| California | Every 3 years, with a visual inspection. Reviewed every year. | Associations whose major components cost at least half the yearly budget, excluding reserves, to replace |
| Florida | Every 10 years: a structural integrity reserve study | Condo and co-op buildings three habitable stories or taller |
| Hawaii | Each year’s budget rests on one. A study not prepared independently is reviewed independently every 3 years. | Condominiums |
| Maryland | Every 5 years, by an independent preparer | Condos, co-ops, and HOAs whose listed components cost $10,000 or more |
| Nevada | Every 5 years, with a summary to the Real Estate Division. Funding reviewed every year. | Common interest communities |
| New Jersey | Every 5 years, with a 30-year funding plan | Associations with $25,000 or more in common area capital assets |
| Oregon | Every year: a study, or a review and update of the last one | Condos of three or more units, and most planned communities |
| Tennessee | Every 5 years. Funding reviewed every year. | Condos under the 2008 act whose common elements cost more than $10,000 to replace |
| Utah | Every 6 years, reviewed and updated every 3 | Condos and HOAs, once the developer has handed over control, unless their documents say otherwise |
| Virginia | Every 5 years. Reviewed every year. | Condos, co-ops and HOAs, unless a condo’s instruments or a co-op’s declaration say otherwise |
| Washington | Updated every year, by a professional after a site visit every third year | Common interest communities, with some exemptions |
Each state’s page has the exact wording, the exemptions and a link to the statute.
Deadlines that have passed
Several of these laws gave older communities a date for their first study, and most of those dates are behind us. Maryland’s ran from October 2021 to October 2023, depending on the county. New Jersey’s was January 8, 2025, and Tennessee’s January 1, 2025. In Florida, the first structural integrity reserve study was due by December 31, 2024 for co-ops and December 31, 2025 for condos. A Florida association whose milestone inspection is due by the end of 2026 may do the study alongside it, but no later than December 31, 2026.
A board that missed one of these dates still needs the study.
Short of a study
Two more states ask for something less than a full study:
- Colorado requires every association to adopt a policy on when it has reserve studies done and how it funds them. Since August 12, 2026, a developer must also commission a reserve study before handing the community over to the owners.
- Minnesota requires its common interest communities to re-evaluate whether their reserves are adequate at least every three years.
Many others require reserves without a study. Delaware’s condos and co-ops must pay into a reserve each year, at the level a reserve study sets or, without one, at 5% to 15% of the budget. Massachusetts condos must keep an “adequate” replacement reserve fund. Illinois and Ohio condo budgets must include reasonable or adequate reserves. Michigan’s condominium rules set a minimum reserve of 10% of the budget. Connecticut, New Hampshire and Vermont ask only that the budget summary show any reserves and how they are worked out.
In twenty-three states and the District of Columbia we found no statewide reserve rule at all. There, the declaration and bylaws decide, and some require reserves even where the law doesn’t.
What to do with one
A reserve study only helps if the board acts on it. Put the next study’s date on the calendar the day this one arrives. Budget the contribution the study recommends, and explain the number to owners when the budget goes out. When a big job comes due, track it against the study’s estimate.
SmartGrouper’s compliance calendar keeps the study’s due date with a link to the rule behind it, and reminds whoever looks after it before it comes round. Big jobs, such as the roof or the façade, keep their contractors, their budget and change orders against what was spent, and the decisions along the way, so the next board inherits the whole history.
To see what your own state requires, look it up.